Question: 1 / 220

What must a VSMP inspector consult to evaluate ESC practices?

The general site management plan

The approved ESC plan for installation and maintenance

To evaluate Erosion and Sediment Control (ESC) practices, a VSMP inspector must consult the approved ESC plan for installation and maintenance. This plan provides detailed guidelines and specifications that outline how effective sediment control and erosion mitigation strategies should be implemented at the site. It includes information about the types of practices to be employed, their placement, maintenance requirements, and operational standards required to minimize soil disturbance and prevent sedimentation into nearby water bodies.

By adhering to the approved ESC plan, the inspector can ensure that the measures in place are compliant with regulations and are being executed properly. This plan serves as a key reference for determining whether the management practices are sufficient to control runoff and sediment loss during construction activities.

The other options do not serve as primary references for evaluating ESC practices. The general site management plan may provide some context but lacks the specific details necessary for assessing erosion and sediment control. Construction contracts contain terms and responsibilities but do not directly address the environmental practices required for sediment control. Nearby environmental reports might offer background information, but they do not provide the necessary guidance for evaluating actual implementation of ESC practices at a specific site.

Get further explanation with Examzify DeepDiveBeta

Construction contracts

Nearby environmental reports

Next Question

Report this question

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy